请高手帮忙翻译,谢谢!请翻译成英语,非常感谢!翻译的好会加赏嘿嘿

1.供应商应於收到此表单[稽核评鉴缺失及改善报告]後,第7个工作天(含)之内回覆EPISTAR,回覆内容至少需涵盖a.[原因分析]、b.[改善对策]及c.[预定完成日].(abc有一项未填写,则视同未回覆).
2.逾期1工作天未回覆EPISTAR,则扣[稽核评鉴分数:2分](2天扣4分,以此类推).
3.EPISTAR收到供应商回覆此表单後,若对其回覆内容有疑虑,则供应商回覆的方式同备注:1.及2.规定处理,但其回覆时效性变更为3个工作天(含).
4.供应商於预定完成日到期前,应主动提供改善结果(佐证)给EPISTAR,逾期1工作天未提供EPISTAR,则扣[稽核评鉴之分数:2分](2天扣4分,以此类推)
5.供应商无法於原[预定完成日]到期前完成缺失改善,需更改[预定完成日]或[改善对策]时,则扣[稽核评鉴之分数:5分](1件缺失扣5分,2件缺失扣10分,以此类推).
6.若属建议事项,则供应商回覆内容至少需涵盖[原因分析].其扣分方式同备注2.规定处理.

1.供应商应於收到此表单[稽核评鉴缺失及改善报告]後,第7个工作天(含)之内回覆EPISTAR,回覆内容至少需涵盖a.[原因分析]、b.[改善对策]及c.[预定完成日].(abc有一项未填写,则视同未回覆). The supplier is to reply to EPISTAR within 7 work days (including the seventh) upon reception of this sheet [Performance Assessment and Improvement Report] and the reply shall at least consist of a. [analysis of causes], b. [countermeasures of improvement] and c. [estimated finishing date]. (In case that any one is missing among the three, it is considered as failure of reply.)
2.逾期1工作天未回覆EPISTAR,则扣[稽核评鉴分数:2分](2天扣4分,以此类推).In case the reply to EPISTAR has not been received 1 work day past the time limit, then the [performance assessment score: 2 points] shall be deducted. (For 2 days overdue, 4 points shall be deducted, and so forth.)
3.EPISTAR收到供应商回覆此表单後,若对其回覆内容有疑虑,则供应商回覆的方式同备注:1.及2.规定处理,但其回覆时效性变更为3个工作天(含). In case that EPISTAR is doubted of the content upon reception of the reply, then the reply made by the supplier shall be in accordance with both remarks No. 1 and No. 2. Meanwhile, the time limit will change to 3 work days. (Including the 3rd.)
4.供应商於预定完成日到期前,应主动提供改善结果(佐证)给EPISTAR,逾期1工作天未提供EPISTAR,则扣[稽核评鉴之分数:2分](2天扣4分,以此类推) The supplier shall provide the result of improvement (with evidence) to EPISTAR before the time limit comes. In case that 1 work day has been passed, then the [performance assessment score: 2 points] shall be deducted. (For 2 days overdue, 4 points shall be deducted, and so forth.)
5.供应商无法於原[预定完成日]到期前完成缺失改善,需更改[预定完成日]或[改善对策]时,则扣[稽核评鉴之分数:5分](1件缺失扣5分,2件缺失扣10分,以此类推). In case that the supplier is unable to complete the improvement on time [before the estimated day of completion] and [the estimated day of completion] or [countermeasures for improvement] needs to be changed , then the [performance assessment score: 5 points] shall be deducted. (In case of one item is delayed, 5 points shall be deducted; For 2 items, 10 points shall be deducted, and so forth.)
6.若属建议事项,则供应商回覆内容至少需涵盖[原因分析].其扣分方式同备注2.规定处理. In case that the reply is within the recommendation category, then the content of the reply shall at least consist of [analysis of causes]. The rule of deduction is identical to that of remarks No. 2.
温馨提示:答案为网友推荐,仅供参考
第1个回答  2011-07-07
1.suppliers should receive this form [audit deficiencies and improve the evaluation report], the first seven days (inclusive) within the response EPISTAR, reply to the content covered at least a. [Analysis], b. [ improvement measures] and c. [scheduled completion date]. (abc does not have a fill, then regarded as not answered)
2. Late one working day did not reply EPISTAR, then buckle [Audit evaluation score: 2] (2 days deducted 4 points, and so on).
3.EPISTAR receive vendor reply to this form, if there are doubts about the content of their reply, the reply in the same way suppliers Note: 1 and 2 regulations, but the response timeliness of changes to three working days (inclusive)
4. supplier before the expiry of the scheduled completion date, should take the initiative to provide improved results (evidence) to EPISTAR, late one working day does not provide EPISTAR, then buckle [Evaluation of Audit Score: 2] (2 days deducted 4 points, and so on)
5.suppliers not on the original [scheduled completion date] due to complete lack of improvement, the need to change the [scheduled completion date] or [improve measures], then buckle [Evaluation of Audit Score: 5] (a missing 5 points, 2 missing 10 points, and so on) 6. If it is the recommended items, the suppliers reply to at least cover the content [Analysis] its points the same way as Remark 2 regulations.
相似回答